Acquire Resources
Inputs, tools & techniques, and outputs for this process.
Securing the people, equipment, materials, facilities, and services the project needs, and confirming their availability and commitments at the right time and cost.
Purpose & When to Use
- Turn planned resource needs into real assignments, contracts, and access so work can start on time.
- Balance skills, capacity, cost, location, and policies to select the best-fit resources.
- Covers internal staff, external vendors, and physical assets like tools, equipment, and facilities.
- Used before each phase or activity that requires resources, and any time replacements or additional resources are needed.
Mini Flow (How It’s Done)
- Review the resource plan, schedule, budget, and sourcing approach to confirm what is needed and when.
- Check internal pools and calendars for available people and assets; identify gaps and constraints.
- Define selection criteria such as skills, experience, cost, availability, time zone, and performance history.
- Decide internal versus external sourcing; negotiate with functional managers or engage procurement as appropriate.
- Assess candidates or suppliers using a transparent decision method; document rationale.
- Secure formal commitments such as assignment approvals, purchase orders, or contracts.
- Prepare onboarding and logistics, including access, tools, licenses, workspace, and initial training.
- If demand exceeds supply, propose trade-offs such as schedule changes, scope adjustments, or phased staffing.
- Update resource calendars, the schedule, cost forecasts, risks, and assumptions; communicate assignments and start dates.
Quality & Acceptance Checklist
- Roles and responsibilities are clear, with required skills and capacity specified.
- Selected resources meet skill, experience, and quality expectations, verified by evidence.
- Availability aligns with planned dates and time commitments; time zone impacts are addressed.
- Costs fit the budget; rates and fees are agreed and approved.
- Formal agreements are in place, such as statements of work, purchase orders, or NDAs.
- Onboarding is complete, including system access, tools, workspace, and compliance training.
- Resource calendars, schedule activities, and cost forecasts are updated and communicated.
- Backups or cross-coverage are identified for critical roles and single points of failure.
- Communication channels and escalation paths are defined for internal and vendor resources.
- Key assumptions and constraints are recorded and understood by stakeholders.
Common Mistakes & Exam Traps
- Mixing up acquiring resources with developing the team or managing team performance.
- Focusing only on people and forgetting equipment, facilities, materials, and services.
- Assuming the project manager can hire directly when negotiation with functional managers or procurement is required.
- Choosing the cheapest option without applying predefined selection criteria and availability checks.
- Starting work before formal commitments, access, and safety or compliance requirements are met.
- Failing to update the schedule, budget, and risk register after resource decisions.
- Ignoring virtual team needs such as time zones, collaboration tools, and communication norms.
- Escalating to the sponsor too early instead of first negotiating or exploring internal options.
PMP Example Question
A critical activity starts next week, but the assigned specialist is now unavailable due to another department’s priority. What should the project manager do first?
- Update the schedule to show a delay and notify stakeholders.
- Escalate to the sponsor to resolve the resource conflict.
- Negotiate with the functional manager to secure an available, equally qualified replacement.
- Submit a change request to reduce scope for the upcoming activity.
Correct Answer: C — Negotiate with the functional manager to secure an available, equally qualified replacement.
Explanation: In acquiring resources, the project manager first seeks internal solutions through negotiation to meet the need and maintain the plan. Baselines or escalations come after attempting viable options.
HKSM