Close Project or Phase
Inputs, tools & techniques, and outputs for this process.
A structured wrap-up that confirms deliverables are accepted, finishes contracts and finances, hands off outcomes to operations, captures lessons learned, updates records, and releases resources to formally end a project or phase.
Purpose & When to Use
This activity brings formal closure to a project or phase. It verifies completion against agreed acceptance criteria, obtains sign-off, transitions deliverables to operations or the next phase, and preserves knowledge for future work. It supports value delivery by ensuring benefits ownership and operational readiness are in place.
- Confirm scope is complete and accepted by authorized stakeholders.
- Transition deliverables to operations, support, or the next phase.
- Close procurements and financials, and release resources.
- Capture lessons learned and archive records for reuse.
- Communicate final results, performance, and benefits readiness.
Use this at the end of every phase and at final project completion, including early termination or cancellation.
Mini Flow (How It’s Done)
- Review the project management plan and closure checklist tailored to the delivery approach (predictive, agile, hybrid).
- Verify that all requirements and deliverables meet acceptance criteria; address any outstanding defects or concessions.
- Obtain formal acceptance and sign-off from the sponsor or authorized customer representative.
- Complete procurements: settle claims, process final invoices, obtain release of liabilities, and document contract closure.
- Transition to operations: deliver handover documents, training, support plans, warranties, and access credentials.
- Close financials: reconcile costs, release remaining funds, account for assets, and update final forecasts and benefits baseline.
- Capture lessons learned through a retrospective; document what to keep, what to change, and why.
- Update repositories: requirements traceability, configuration records, test evidence, approvals, and final baseline.
- Release team members and other resources; complete performance feedback and administrative closeout.
- Issue a final report summarizing scope, schedule, cost, quality, risks, benefits readiness, and outstanding follow-up actions.
Quality & Acceptance Checklist
- All deliverables verified against criteria and defects resolved or formally waived.
- Formal acceptance/sign-off recorded by the authorized stakeholder.
- Requirements traceability matrix shows complete status and final disposition for each requirement.
- Configuration items updated; final versions and baselines are stored and accessible.
- Test results, quality records, and compliance evidence archived.
- Operational readiness confirmed: procedures, training, support model, SLAs, and contact points in place.
- Data migration or cutover executed and validated, with rollback outcomes documented.
- Contracts closed: final payments made, claims settled, and closeout certificates filed.
- Financial closure complete: budgets reconciled, assets recorded, and remaining funds released.
- Risks and issues closed or formally transferred with owners and due dates.
- Lessons learned captured, shared, and indexed for search in the knowledge base.
- Stakeholders notified of closure; final report and archives communicated and stored.
Common Mistakes & Exam Traps
- Skipping formal acceptance; always get documented sign-off from the authorized person.
- Releasing the team before closing procurements and financials.
- Treating closure as paperwork only; ensure a real operational handover and support readiness.
- Leaving change requests, defects, or claims unresolved; decide, defer with agreement, or close them.
- Confusing phase closure with project closure; in phase closure, only the phase is closed and resources may continue into the next phase.
- Failing to transfer benefits measurement and ownership to the appropriate operational owner.
- Not updating configuration records and repositories, causing future support gaps.
- Ignoring early-termination steps; canceled projects still require full closure activities.
- For adaptive approaches, forgetting to document the status of remaining backlog items and transition plans.
PMP Example Question
A project’s deliverables are accepted by the customer, but a vendor has a small unresolved claim. What should the project manager do next before releasing the team?
- Release the team and let procurement handle the claim separately.
- Archive documents and close the project since acceptance is complete.
- Work with procurement to settle the claim and complete contract closure, then finish project closure activities.
- Ignore the claim because it is minor and proceed with closure.
Correct Answer: C — Work with procurement to settle the claim and complete contract closure, then finish project closure activities.
Explanation: All procurements must be closed and claims resolved or formally settled before releasing resources and completing project closure.
HKSM