Closing Focus Area
The closing focus area includes the activities required to formally complete a project or phase, confirm acceptance of deliverables, release resources, and capture lessons learned.
What is the Closing Focus Area?
The closing focus area ensures that the project or phase is brought to an orderly conclusion. It focuses on confirming that objectives have been met, obtaining formal acceptance of deliverables, completing administrative tasks, and capturing knowledge for future work. Proper closing prevents loose ends, unresolved obligations, and loss of valuable learning.
Key concepts
- Formal acceptance: documented confirmation that deliverables meet acceptance criteria.
- Administrative closure: updating records, archiving documents, and finalizing contracts.
- Resource release: returning team members, equipment, and facilities to the organization.
- Lessons learned: identifying what worked well and what should be improved next time.
- Benefits handover: ensuring that owners of operations or business units are ready to realize benefits.
Common pitfalls and exam traps
- Disbanding the team as soon as major deliverables are deployed, without formal closure.
- Skipping lessons learned sessions because the team is eager to move on.
- Failing to close contracts properly, leading to future disputes or unexpected costs.
- Not obtaining written acceptance from the customer or sponsor.
- Exam trap: treating the project as “done” when work stops, even if administrative closure is incomplete.
PMP Example Question
PMP Example Question
The project’s final deliverables have been installed and are functioning as expected. The sponsor verbally confirms satisfaction and asks the project manager to move on to a new initiative. What should the project manager do next?
- Immediately release the project team and start planning the new initiative.
- Conduct a formal closure process, including documented acceptance and lessons learned.
- Skip closure activities because the sponsor is already satisfied.
- Transfer all remaining work informally to the operations team.
Correct Answer: B — Conduct a formal closure process, including documented acceptance and lessons learned.
Explanation:The closing focus area requires formal completion of the project or phase, including documented acceptance, administrative closure, and knowledge capture. Simply relying on verbal confirmation or skipping closure activities can leave obligations and learning unresolved.
HKSM