Governance
Governance is the set of policies, decision rights, and oversight mechanisms that guide how a project is directed, authorized, and controlled so that it aligns with organizational objectives and constraints.
Why this domain matters
Governance ensures that projects are not run as isolated side efforts, but are aligned with strategy, follow organizational policies, and use transparent decision-making. Good governance clarifies who can approve changes, how issues are escalated, and what information leaders need to make decisions, reducing political conflict and surprise decisions late in the project.
Key concepts
- Governance framework: policies, standards, and decision-making structures that guide projects across the organization.
- Decision rights: clarity on who can approve scope, budget, schedule changes, and major risk responses.
- Governance bodies: steering committees, sponsors, and review boards that provide direction and oversight.
- Escalation paths: predefined routes to raise issues, risks, and decisions when they exceed the project manager’s authority.
- Compliance and controls: ensuring projects follow legal, regulatory, security, and internal policy requirements.
Common pitfalls and exam traps
- Running the project based only on the sponsor’s preferences and ignoring formal governance processes.
- Escalating issues informally to senior leaders instead of using the defined escalation path and decision forums.
- Approving changes in stakeholder meetings without updating the decision log or following change control procedures.
- Confusing project management processes with governance, and treating governance as optional documentation.
- Exam trap: choosing “talk to the team” or “update the plan” when the correct first action is to follow the governance framework or escalate to the proper body.
PMP Example Question
PMP Example Question
A project manager discovers that a major scope change is being pushed by a powerful stakeholder through informal conversations. The change will significantly impact cost and schedule. What should the project manager do first?
- Update the project management plan to reflect the new scope.
- Ask the sponsor for verbal approval and proceed with the change.
- Submit the change through the formal change control process defined in the governance framework.
- Negotiate directly with the stakeholder to reduce the scope of the change.
Correct Answer: C — Submit the change through the formal change control process defined in the governance framework.
Explanation: Governance requires that significant changes follow the established decision-making process and are reviewed by the appropriate authority, often through integrated change control. Updating the plan without approval, relying on informal verbal approval, or negotiating privately bypasses the governance framework and can lead to misalignment, disputes, and loss of control.
HKSM