Decision tree analysis
Decision tree analysis is a quantitative technique that models choices and uncertain events to compare alternatives using probabilities and payoffs. It typically applies expected monetary value and rollback calculations to identify the risk-adjusted best option.
Key Points
- Visual model that maps decisions (squares) and uncertain events (circles) with branches for outcomes.
- Compares alternatives by calculating expected monetary value (EMV) and rolling back the tree from right to left.
- Useful for risk response selection, vendor choice, make-or-buy, and go/no-go decisions.
- Requires clear assumptions: probabilities that are complete and mutually exclusive, and monetized outcomes.
- Can include mitigation costs, residual risk, and value of information (e.g., paying for a test before deciding).
- Informs, but does not replace, judgment, risk appetite, and non-financial constraints.
Purpose of Analysis
Provide a structured, quantitative way to choose among alternatives under uncertainty by combining probabilities and impacts. It helps justify decisions, compare risk-adjusted costs or benefits, and communicate trade-offs transparently to stakeholders.
Method Steps
- Define the decision objective and whether you are minimizing cost or maximizing value.
- List feasible alternatives and decision criteria.
- Identify uncertain events and mutually exclusive states for each branch.
- Estimate probabilities using expert judgment, historical data, or models.
- Estimate monetary outcomes for each end path, including costs, benefits, penalties, and residual risk.
- Draw the tree with decision and chance nodes; annotate probabilities and payoffs.
- Compute EMV at each chance node by summing probability × payoff across branches.
- Roll back from right to left, selecting the branch with the best EMV at each decision node.
- Perform sensitivity analysis on key probabilities and impacts; consider utility or constraints if risk tolerance is a factor.
- Document assumptions, data sources, and rationale.
Inputs Needed
- Defined alternatives and decision criteria.
- Probability estimates for each state of uncertainty, including conditional probabilities when applicable.
- Impact estimates (costs, benefits, penalties, rework, savings).
- Costs and effects of risk responses or tests, and residual risk after responses.
- Time value of money assumptions (discount rate) for multi-period cash flows.
- Risk register entries, historical data, and expert judgment.
- Constraints, risk thresholds, and utility or preference considerations.
Outputs Produced
- Recommended alternative based on EMV and rollback results.
- EMV calculations for each path and a clear decision tree diagram.
- Sensitivity analysis results and break-even conditions.
- Documented assumptions, probabilities, and data sources.
- Optional: value of information metrics (EVPI/EVSI) to assess whether additional analysis or testing is worth the cost.
Interpretation Tips
- For cost-focused problems, choose the lowest expected cost; for value-focused problems, choose the highest EMV.
- Use consistent units by monetizing schedule or quality impacts where practical.
- Ensure probabilities are complete and appropriate (mutually exclusive and collectively exhaustive); handle conditional probabilities carefully.
- Consider risk appetite: EMV may not reflect stakeholder utility for one-time, high-impact risks.
- Run sensitivity tests to identify inputs that could flip the decision and to gauge robustness.
- Update the tree as new information arrives; revise probabilities rather than forcing outcomes.
Example
A team must select a vendor. Vendor A offers a fixed price of $300,000 with a 30% chance of a $50,000 delay penalty. Vendor B is time-and-materials with an expected base cost of $260,000 and a 40% chance of an $80,000 scope increase.
- Vendor A EMV (cost) = 300,000 + 0.30 × 50,000 = 315,000.
- Vendor B EMV (cost) = 260,000 + 0.40 × 80,000 = 292,000.
- Decision: Choose Vendor B because it has the lower expected cost.
Pitfalls
- Overprecision: assigning exact-looking numbers to weak estimates, creating false confidence.
- Incomplete or overlapping states that cause probabilities not to sum correctly.
- Ignoring correlations or double-counting risks across branches.
- Relying solely on EMV for single, high-impact decisions without considering utility or constraints.
- Omitting time value of money or lifecycle effects for multi-period outcomes.
- Overly complex trees that are hard to validate and explain to stakeholders.
PMP Example Question
A project manager is evaluating whether to implement a $40,000 mitigation that eliminates a 25% chance of a $200,000 failure. Using decision tree analysis, what should the PM recommend?
- Implement mitigation because its expected cost (40,000) is lower than the expected failure cost (0.25 × 200,000 = 50,000).
- Do not mitigate because it adds certain cost now.
- Perform qualitative risk analysis first and postpone any decision.
- Escalate the decision to the sponsor due to uncertainty.
Correct Answer: A — Implement mitigation because its expected cost is lower than the expected loss.
Explanation: Decision tree analysis compares EMVs; the mitigation has an EMV of 40,000, which is less than the 50,000 expected loss if the risk is accepted.
HKSM