Schedule baseline
The schedule baseline is the approved, time-phased plan for the project's activities, milestones, and key dates. It is the fixed reference used to measure schedule performance, manage variances, and control changes.
Key Points
- The schedule baseline is the authorized snapshot of the schedule model used for performance measurement and control.
- It is established after schedule development and formal approval, and changes require change control.
- It includes planned start and finish dates for activities and milestones, and reflects the critical path at approval time.
- Progress is compared to the baseline to identify variances, trends, and need for corrective or preventive actions.
- Re-baselining is rare and only done when significant, approved changes justify resetting the plan.
- The baseline is stored, version-controlled, and referenced in reports and forecasts.
Purpose
The schedule baseline provides a clear, agreed plan for when work should happen so the team and stakeholders share the same expectations. It enables consistent tracking, variance analysis, forecasting, and transparent decision-making when changes are proposed.
Pre-requisites
- Defined scope baseline (scope statement, WBS, and WBS dictionary).
- Complete activity list with attributes and logical relationships.
- Resource assignments, calendars, and availability confirmed.
- Duration estimates and documented estimating assumptions.
- Risk analysis completed with time buffers or schedule reserves defined.
- Schedule management plan with performance thresholds and measurement methods.
- Stakeholder review of constraints, milestones, and acceptance of planning assumptions.
How to Set Baseline
- Build a resource-feasible schedule model and validate logic, critical path, and float.
- Apply calendars, constraints sparingly, and verify no dangling or open-ended activities.
- Incorporate risk responses with appropriate buffers and schedule reserves.
- Run what-if analyses and adjust the plan to meet objectives and constraints.
- Define the data date, reporting cycle, coding structures, and earned value method if used.
- Document assumptions, exclusions, and the baseline version and date.
- Review with the team and stakeholders; resolve conflicts and resource overloads.
- Obtain formal approval through integrated change control and freeze the baseline.
- Store the baseline in the scheduling tool and configuration system, and communicate it.
How to Use
- Capture actuals and forecasts routinely, and compare to baseline dates and milestones.
- Analyze variances and trends at the activity, path, and milestone levels.
- Apply thresholds to trigger corrective or preventive actions or change requests.
- Use the baseline to communicate impacts, negotiate trade-offs, and support decisions.
- Maintain the baseline unchanged unless an approved re-baseline is authorized.
- Align status updates and reports (e.g., milestone trend charts, SPI) to the baseline.
Change Control Rules
- Any change that alters approved milestone dates or the critical path requires a change request.
- Assess impacts on scope, cost, resources, risks, and benefits before approval.
- Use defined thresholds to determine when to escalate versus handle within management reserves and authority.
- Preserve previous baseline versions and maintain traceability in the change log.
- Only re-baseline when significant, approved changes or resets make the current baseline no longer useful.
- Synchronize updates with related baselines (scope and cost) to keep the plan coherent.
Example
A project is approved with a 10-month schedule baseline and four quarterly milestones. At month 4, a critical activity slips by three weeks. The team analyzes the variance, tests schedule compression and resequencing options, and determines a five-day delay to Milestone 2 remains. The project manager raises a change request with impact analysis; once approved, the updated baseline reflects the new milestone date and is communicated to stakeholders.
PMP Example Question
Midway through execution, a supplier delay pushes the critical path by 12 days. What should the project manager do next with respect to the schedule baseline?
- Update the schedule baseline to reflect the new dates and notify stakeholders.
- Analyze impacts and submit a change request per the change control process.
- Compress the schedule by adding overtime and skip approvals to save time.
- Escalate to the sponsor to decide whether to continue the project.
Correct Answer: B — Analyze impacts and submit a change request per the change control process.
Explanation: The schedule baseline can only be changed through formal change control. The next step is to assess impacts and seek approval before altering the baseline dates.
HKSM