Work performance information
Work performance information is analyzed, contextualized results about project performance derived from raw data, showing status, trends, variances, and forecasts for decision-making. It links actual results to the plan so stakeholders understand what is happening and why.
Key Points
- Transforms raw performance data into insights by adding analysis, comparisons to baselines, and context.
- Summarizes status, variances, trends, forecasts, and the implications for scope, schedule, cost, quality, and risks.
- Continuously produced during delivery and control activities, then refined as more data arrives.
- Tailored to stakeholder needs; level of detail, frequency, and visualization vary by audience.
- Feeds governance, change control, and stakeholder reporting, and supports timely decisions.
- Must be accurate, timely, and traceable back to the original data and measurement methods.
Purpose
- Provide clear insight into how the project is performing against the plan.
- Enable proactive decisions, such as corrective actions, preventive actions, and change requests.
- Highlight trends and risks early to protect outcomes and value delivery.
- Support transparent communication with sponsors, teams, and other stakeholders.
Data Sources
- Work performance data from team updates, time tracking, and tools (e.g., task completion, effort, throughput).
- Schedule data: milestones achieved, critical path changes, SPI, lead/lag observations.
- Cost data: actual costs, commitments, CPI, burn rate, EAC forecasts.
- Quality results: test outcomes, defect density, rework rates, audit findings.
- Risk and issue logs: triggers observed, risk responses executed, issue impact and aging.
- Change log and configuration records: approved changes, pending requests, scope impacts.
- Procurement and vendor performance: deliveries, SLAs, acceptance status.
- Baseline documents and the current plan for variance comparisons.
How to Compile
- Collect current work performance data from systems and team reports at the agreed cadence.
- Validate and clean the data to remove errors and ensure consistent definitions and timeframes.
- Compare actuals to baselines and targets; compute key variances and indices (e.g., SPI, CPI) as relevant.
- Analyze trends and drivers: look for patterns, constraints, resource bottlenecks, and emerging risks.
- Add context and interpretation: explain causes, effects, and likely outcomes if no action is taken.
- Generate concise visuals or summaries suited to each audience and link back to source data.
- Review with the team or PMO for accuracy and alignment before broader distribution.
How to Use
- Guide decisions in governance meetings and daily team forums.
- Trigger corrective or preventive actions and inform change requests when thresholds are exceeded.
- Update forecasts and replan work based on validated trends and constraints.
- Communicate status to stakeholders through dashboards, reports, or briefings.
- Capture lessons learned about metrics, thresholds, and effective responses.
Sample View
A concise weekly snapshot might include:
- Scope: 42 of 50 planned backlog items completed this iteration (84%).
- Schedule: SPI = 0.93; critical path slipped by 3 days due to dependency delay.
- Cost: CPI = 1.02; EAC trending at 98% of budget.
- Quality: 12 defects found, 9 fixed; defect escape rate decreasing for 3 consecutive weeks.
- Risks/Issues: High-risk supplier delay mitigated; one new issue may impact next milestone.
- Forecast: Milestone M3 projected 1 week late without resource leveling; mitigation proposed.
Interpretation Tips
- Always compare to the right baseline and time window to avoid false signals.
- Focus on trends and drivers, not just single-point variances or vanity metrics.
- Use both leading indicators (flow, throughput, cycle time) and lagging indicators (SPI, CPI).
- Seek root causes before recommending actions; avoid overreacting to outliers.
- Pair quantitative metrics with qualitative context from the team and stakeholders.
- Ensure traceability from insights back to source data and calculation methods.
PMP Example Question
During a review, the sponsor asks for information that explains why the schedule is slipping and what will happen if no action is taken. Which artifact best meets this need?
- Work performance data.
- Work performance information.
- Work performance reports.
- Issue log.
Correct Answer: B — Work performance information.
Explanation: Work performance information adds analysis and context (variances, trends, forecasts). Data is raw figures; reports are formatted communications created from the information.
HKSM