Implement Risk Responses

Risk/Executing/Implement Risk Responses
Inputs Tools & Techniques Outputs

Inputs, tools & techniques, and outputs for this process.

Carrying out agreed actions to address threats and opportunities, integrating them into project work, and adjusting plans through change control so that overall risk exposure stays within acceptable limits.

Purpose & When to Use

  • Turn planned risk responses into action to reduce threats and maximize opportunities.
  • Activate responses when triggers occur or when scheduled as proactive actions.
  • Use throughout delivery once responses are approved, especially after risk reviews or new risk identification.
  • Keep overall risk exposure aligned with organizational risk appetite and thresholds.

Mini Flow (How It’s Done)

  • Confirm each risk's owner, chosen response strategy, trigger conditions, and success criteria.
  • Break the response into executable tasks; add them to the schedule or backlog with clear due dates.
  • Secure resources and funding; if baselines are impacted, submit a change request and obtain approval before execution.
  • Update the risk register with actions, owners, triggers, costs, and measures of effectiveness.
  • Communicate responsibilities and timing to the team and stakeholders; align with procurement and vendors if applicable.
  • Execute the response when conditions are met or as planned; use reserves according to pre-approval rules.
  • Track effectiveness with agreed metrics; adjust or implement fallback if the response underperforms.
  • Identify and manage any secondary or residual risks created by the response.
  • For realized risks, log as issues and coordinate workarounds while pursuing planned responses or change control as needed.
  • Update artifacts and reports; close responses once objectives are met and capture lessons learned.

Quality & Acceptance Checklist

  • Response owner is named and accountable.
  • Entry trigger and exit criteria are documented and understood.
  • Tasks are integrated into the schedule or backlog with dependencies and resources assigned.
  • Budget, reserves, and procurement actions are confirmed and available.
  • Required change requests are approved and baselines updated before execution.
  • Stakeholders are informed about actions, timing, and impacts.
  • Effectiveness measures are defined, monitored, and recorded as evidence.
  • Residual risk is within agreed thresholds or a new plan is in place.
  • Secondary risks are identified, evaluated, and assigned for action.
  • Risk register, issue log, status reports, and lessons learned are updated.

Common Mistakes & Exam Traps

  • Confusing implement, plan, and monitor activities; implementation is about doing the actions, not selecting them or reviewing them.
  • Executing changes that affect baselines without going through change control.
  • Treating realized risks as risks instead of logging them as issues and acting immediately.
  • Focusing only on threats and ignoring opportunity responses such as exploit or enhance.
  • Failing to define triggers and owners, leading to missed or late activation.
  • Ignoring secondary and residual risks created by the response.
  • Escalating to leadership without documenting the response or following governance.
  • Overlooking supplier or contract updates when responses rely on external parties.
  • Exam trap: choosing to “update the risk management plan” when the question asks what to do next during execution; the right move is to carry out the approved response or raise a change request if baselines are impacted.

PMP Example Question

A risk trigger has occurred. The approved response adds testing tasks not included in the current baseline. What should the project manager do next?

  1. Add the tasks to the schedule and start work to avoid delay.
  2. Submit a change request to update the schedule and budget, then implement the response after approval.
  3. Update the risk register and wait for the next risk review meeting.
  4. Escalate the risk to the sponsor for direction.

Correct Answer: B — Submit a change request to update the schedule and budget, then implement the response after approval.

Explanation: If a response changes baselines, follow change control before execution. Only pre-approved actions within reserves can proceed without additional approval.

AI-Prompt Engineering for Strategic Leaders

Stop managing administration and start leading the future. This course is built specifically for managers and project professionals who want to automate chaos and drive strategic value using the power of artificial intelligence.

We don't teach you how to program Python; we teach you how to program productivity. You will master the AI-First Mindset and the 'AI Assistant' model to hand off repetitive work like status reports and meeting minutes so you can focus on what humans do best: empathy, negotiation, and vision.

Learn the 5 Core Prompt Elements-Role, Goal, Context, Constraints, and Output-to get high-quality results every time. You will build chained sequences for complex tasks like auditing schedules or simulating risks, while navigating ethics and privacy with human-in-the-loop safeguards.

Move from being an administrative manager to a high-value strategic leader. Future-proof your career today with practical, management-focused AI workflows that map to your real-world challenges. Enroll now and master the language of the future.



Launch your career!

HK School of Management provides world-class training in Project Management, Lean Six Sigma, and Agile Methodologies. Just for the price of a lunch you can transform your career, and reach new heights. With 30 days money-back guarantee, there is no risk.

Learn More