4.1 Develop Project Charter
| 4.1 Develop Project Charter | ||
|---|---|---|
| Inputs | Tools & Techniques | Outputs |
Replace this with term.
Purpose & When to Use
- Authorize the project or phase so work can officially start.
- State the problem or opportunity, expected benefits, and measurable objectives.
- Name the sponsor and project manager, and clarify decision and spending authority.
- Summarize scope boundaries, key milestones, budget limits, major risks, and assumptions.
- Align the initiative with organizational strategy and funding.
- Use at the very start of a project or phase, and update only if there is a major shift in direction.
Mini Flow (How It’s Done)
- Review the business case, agreements, and any prior analyses to understand the need and benefits.
- Hold a short workshop with the sponsor and key stakeholders to agree on vision, objectives, and success criteria.
- Define high-level scope and boundaries, major deliverables, and what is explicitly out of scope.
- Outline major milestones, target completion date, and funding cap or budget range.
- Capture key risks, assumptions, constraints, and known dependencies.
- Document governance: roles, escalation path, decision rights, and the project manager’s authority.
- Draft the charter using the organizational template or lessons learned from similar projects.
- Validate the draft with stakeholders, resolve conflicts, and refine content.
- Obtain formal sponsor approval and signatures to authorize the project.
- Communicate the approved charter to stakeholders and store it in the project repository.
Quality & Acceptance Checklist
- Clear business need and linkage to strategy or benefits are stated.
- Objectives are specific and measurable, with success criteria and target dates.
- Scope boundaries and major deliverables are summarized, including what is out of scope.
- Budget limit or funding approach is identified, with a high-level cost estimate if available.
- High-level schedule and milestone map are included.
- Key risks, assumptions, and constraints are listed.
- Sponsor, project manager, and key roles are named with decision and spending authority clarified.
- Governance and escalation path are described.
- Dependencies on other initiatives or external parties are noted.
- Approval method and signatures are captured, with version control information.
- References to the business case, agreements, or feasibility studies are included.
- Communication expectations for kickoff and early stakeholder engagement are defined.
Common Mistakes & Exam Traps
- Confusing the charter with the project management plan; the charter is brief and high level.
- Starting detailed planning or execution without sponsor authorization.
- Overloading the charter with task-level details or fully developed baselines.
- Failing to state the project manager’s authority and decision rights.
- Ignoring key stakeholders during drafting, leading to misaligned objectives.
- Not linking objectives to measurable success criteria and expected benefits.
- Copying a template without tailoring to actual constraints and risks.
- Overlooking external agreements or contracts that drive scope and constraints.
- Assuming the project manager creates and approves the charter alone; the sponsor authorizes it.
- Forgetting that the charter can be lightweight in adaptive life cycles while still giving direction and authority.
PMP Example Question
A team begins work to meet an aggressive deadline, but there is no signed project charter. What should the project manager do next?
- Continue work and create a detailed schedule to control progress.
- Hold a risk workshop to identify early threats and opportunities.
- Work with the sponsor to obtain formal authorization and approve the charter.
- Start developing the project management plan to guide the team.
Correct Answer: C — Work with the sponsor to obtain formal authorization and approve the charter.
Explanation: Without an approved charter, the project lacks official authorization and authority. The immediate action is to secure sponsor approval before continuing work.
HKSM