5.12 Estimate Costs

5.12 Estimate Costs
Inputs Tools & Techniques Outputs

Replace this with term.

Purpose & When to Use

  • Develop a realistic view of how much the project work will cost so leaders can plan funding, compare options, and set expectations early.
  • Used during planning to estimate at activity or work package level, then refined as scope, design, and quotes mature.
  • Revisited when scope changes, risks evolve, procurement information arrives, or market rates shift.
  • Outputs inform the budget baseline process and provide the basis for future cost control.

Mini Flow (How It’s Done)

  • Collect inputs: scope baseline and WBS, activity list and durations, resource needs and rates, procurement strategy and quotes, risk register, lessons learned, cost policies, taxes, and currency assumptions.
  • Select estimating approaches: analogous for quick top-down comparisons, parametric for rate-based calculations, three-point for uncertainty, and bottom-up for detailed rollups.
  • Obtain market data and vendor pricing where relevant, and analyze bids when multiple offers exist.
  • Include quality-related costs, indirects, fees, and life-cycle considerations if required by the business case.
  • Calculate activity or work package costs, document assumptions and methods, and show ranges and confidence levels.
  • Apply risk-based contingency using reserve analysis, and identify any management reserve held by sponsors if applicable.
  • Aggregate estimates to work packages and control accounts aligned to the WBS, time-phase them to the schedule, and reconcile with funding limits.
  • Produce cost estimates and a clear basis of estimate, and update the risk register and documents as needed.

Quality & Acceptance Checklist

  • Each WBS item has an estimate that matches its defined scope and resources.
  • Chosen estimating methods are appropriate for the data available and are explained clearly.
  • Rates, units, and quantities are validated, current, and sourced.
  • Assumptions, constraints, and exclusions are documented and traceable.
  • Direct, indirect, procurement, logistics, taxes, and cost of quality are considered.
  • Currency, inflation, and escalation factors are addressed when relevant.
  • Risk-based contingency is calculated and linked to specific risks; no double counting with management reserve.
  • Estimates are time-phased and consistent with the schedule.
  • Estimate ranges and confidence levels are provided where uncertainty exists.
  • Peer review completed and stakeholder acceptance recorded.

Common Mistakes & Exam Traps

  • Confusing Estimate Costs (activity-level estimating) with Determine Budget (aggregating and setting the cost baseline).
  • Providing single-point numbers without a basis, range, or confidence level.
  • Ignoring indirect costs, cost of quality, or life-cycle impacts when required.
  • Mixing up contingency (for identified risks) with management reserve (for unforeseen work).
  • Double counting reserves or applying contingency at multiple rollup levels.
  • Using analogous estimates when detailed data is available for bottom-up or parametric methods.
  • Failing to refresh estimates after design changes or new vendor quotes.
  • Choosing the lowest bid without analyzing total cost of ownership and risk.
  • Overlooking currency conversions, inflation, or timing effects on cash flow.
  • Assuming earned value techniques are used during estimating rather than during monitoring and control.

PMP Example Question

The sponsor asks for a quick cost figure early in planning to compare alternatives. Detailed design is not yet available. Which technique is most appropriate?

  1. Analogous estimating.
  2. Bottom-up estimating.
  3. Vendor bid analysis.
  4. Earned value analysis.

Correct Answer: A — Analogous estimating.

Explanation: Analogous uses historical data for fast, top-down estimates when detail is limited. Bottom-up needs detailed scope, vendor bid analysis applies to procurements, and earned value is for performance tracking, not estimating.

Advanced Lean Six Sigma — Data-Driven Excellence

Solve complex problems, reduce variation, and improve performance with confidence. This course is designed for professionals who already know the basics and want to apply advanced Lean Six Sigma tools to real business challenges.

This is not abstract statistics or theory-heavy training. You’ll use Excel to perform real analysis, interpret results correctly, and apply tools like DMAIC, SIPOC, MSA, hypothesis testing, and regression without memorizing formulas or relying on expensive software.

You’ll learn how to measure baseline performance, analyze process capability, use control charts to maintain stability, and validate improvements using statistical evidence. Templates, worked examples, and structured walkthroughs help you apply each concept immediately.

Learn through a complete, real-world Lean Six Sigma project and develop the skills to lead data-driven improvements with credibility. If you’re ready to move beyond basics and make decisions backed by data, enroll now and take your Lean Six Sigma expertise to the next level.



Take Control of Project Performance!

HK School of Management helps you go beyond status reports and gut feelings. In this advanced course, you’ll master Earned Value Management (EVM) to objectively measure progress, forecast outcomes, and take corrective action with confidence. Learn how WBS quality drives performance, how control accounts really work, and how to use EAC, TCPI, and variance analysis to make smarter decisions—before projects drift off track. Built around real-world examples and hands-on exercises, this course gives you practical tools you can apply immediately. Backed by our 30-day money-back guarantee—low risk, high impact for serious project professionals.

Learn More