5.8 Sequence Activities

5.8 Sequence Activities
Inputs Tools & Techniques Outputs

Replace this with term.

Purpose & When to Use

Sequence Activities organizes the activity list into a logical order so work can flow efficiently. It defines how tasks relate (what must happen before or alongside what), enabling creation of a network diagram and later the critical path. Use this after the activity list is defined and before estimating durations and developing the schedule.

Mini Flow (How It’s Done)

  • Review the activity list, activity attributes, and milestone list to understand all work items.
  • Identify dependencies: mandatory (by nature of the work), discretionary (best practice or preference), and external (outside parties or events).
  • Select relationship types between activities: Finish-to-Start (FS), Start-to-Start (SS), Finish-to-Finish (FF), or Start-to-Finish (SF).
  • Apply leads and lags where justified, documenting the reason and the amount (e.g., SS with 2-day lag).
  • Capture constraints and assumptions that affect ordering, and note external or cross-team links.
  • Build the network diagram, aiming for a clear single start and single finish path where practical.
  • Validate logic with the team and stakeholders; look for loops, open ends, and unnecessary constraints.
  • Update activity attributes with predecessors, successors, relationship types, and lead/lag details.
  • Record changes to risks and assumptions that arise from dependencies (e.g., supplier timing risk).

Quality & Acceptance Checklist

  • Every activity (except project start/finish milestones) has at least one predecessor or successor recorded.
  • Relationship types are correct and minimal; FS is used by default unless SS, FF, or SF adds needed realism.
  • Leads and lags have numeric values and documented reasons; they are not used to hide missing work.
  • Discretionary dependencies are explicitly labeled and can be changed if schedule compression is needed.
  • Hard date constraints are avoided unless truly required; logic, not dates, drives the sequence.
  • The network diagram has no loops and no dangling activities; paths are traceable end to end.
  • External dependencies are identified, documented, and linked to risk responses and monitoring.
  • Updates to the assumptions log and risk register reflect key dependency uncertainties.
  • Traceability to the WBS is maintained so scope changes can be reflected in activity logic.

Common Mistakes & Exam Traps

  • Using fixed dates instead of logical links, which weakens the schedule and hides true drivers.
  • Overusing leads (negative lag) to force overlap rather than modeling additional activities.
  • Leaving open ends: activities without predecessors or successors, causing broken network paths.
  • Misapplying relationship types; for example, using FF when the intent is to start work in parallel (SS).
  • Skipping team validation and relying on one person’s view of the sequence.
  • Ignoring external dependencies and not reflecting them as risks with monitoring actions.
  • Confusing processes: sequencing orders activities; estimating durations and resource assignments come later.
  • Mixing up visuals: a network diagram shows logic; a Gantt chart shows timing after durations are applied.
  • Treating lags as percentages; lags and leads should be defined in measurable time or effort units.

PMP Example Question

The team wants testing to begin two days after development starts, with both activities running in parallel. Which relationship should the scheduler use?

  1. Finish-to-Start with a 2-day lead.
  2. Start-to-Start with a 2-day lag.
  3. Finish-to-Finish with a 2-day lag.
  4. Start-to-Finish with a 2-day lag.

Correct Answer: B — Start-to-Start with a 2-day lag.

Explanation: SS with a 2-day lag starts the successor two days after the predecessor begins. FS with a lead references finish, not start, and would not tie the start times as required.

Advanced Lean Six Sigma — Data-Driven Excellence

Solve complex problems, reduce variation, and improve performance with confidence. This course is designed for professionals who already know the basics and want to apply advanced Lean Six Sigma tools to real business challenges.

This is not abstract statistics or theory-heavy training. You’ll use Excel to perform real analysis, interpret results correctly, and apply tools like DMAIC, SIPOC, MSA, hypothesis testing, and regression without memorizing formulas or relying on expensive software.

You’ll learn how to measure baseline performance, analyze process capability, use control charts to maintain stability, and validate improvements using statistical evidence. Templates, worked examples, and structured walkthroughs help you apply each concept immediately.

Learn through a complete, real-world Lean Six Sigma project and develop the skills to lead data-driven improvements with credibility. If you’re ready to move beyond basics and make decisions backed by data, enroll now and take your Lean Six Sigma expertise to the next level.



Advance your Lean Six Sigma expertise!

HK School of Management helps you take Lean Six Sigma to the next level—without the overwhelm. Master advanced statistical tools, Excel-based analysis, and real-world improvement techniques to solve complex problems with confidence. For the price of lunch, you get practical templates, guided examples, and hands-on project experience you can use immediately at work. Backed by our 30-day money-back guarantee—zero risk, real impact.

Learn More