Dependency

A dependency describes how two activities are linked so that one must start or finish before, after, or with the other; it sets the required order and timing between a predecessor and a successor.

Key Points

  • Four patterns describe timing: finish-to-start (FS), start-to-start (SS), finish-to-finish (FF), and start-to-finish (SF).
  • Origins include mandatory (hard), discretionary (preferred/soft), external, and internal dependencies.
  • Leads and lags adjust overlap or waiting time between linked activities without changing the underlying logic.
  • See logical relationship.

Example

In a construction project, "Frame walls" cannot begin until "Foundation cured" is complete, plus a 2-day wait for curing. This is an FS dependency with a 2-day lag.

PMP Example Question

Activity B must wait until Activity A finishes, and then there is a planned 2-day curing period before B can start. What best describes this relationship?

  1. Finish-to-Start with a 2-day lag
  2. Start-to-Start with a 2-day lead
  3. Finish-to-Finish with a 2-day lag
  4. Discretionary internal dependency with a lead

Correct Answer: A — Finish-to-Start with a 2-day lag

Explanation: B can start only after A has finished, and a waiting period is inserted; that is an FS relationship with lag.

AI for Project Managers — Build Plans Faster, Lead Better

Turn messy inputs into structured project plans in minutes. If you are a project manager tired of spending hours on documentation, this course shows you how to use AI to work faster while staying fully in control.

This is not a generic AI course. You will learn how to use AI as a practical co-pilot to build real project artifacts—charters, WBS, schedules, risk registers, and executive reports—using structured, reliable prompt frameworks.

You will also learn how to keep your project aligned across scope, schedule, cost, and risk, and how to interpret performance data like Earned Value Management to support better decisions and communication.

Everything is designed for immediate use. You get ready-to-use prompt templates and workflows you can apply right away in your projects. Watch the video to see how it works and start building your first AI-supported project plan.



Take Control of Project Performance!

HK School of Management helps you go beyond status reports and gut feelings. In this advanced course, you’ll master Earned Value Management (EVM) to objectively measure progress, forecast outcomes, and take corrective action with confidence. Learn how WBS quality drives performance, how control accounts really work, and how to use EAC, TCPI, and variance analysis to make smarter decisions—before projects drift off track. Built around real-world examples and hands-on exercises, this course gives you practical tools you can apply immediately. Backed by our 30-day money-back guarantee—low risk, high impact for serious project professionals.

Learn More