Late Finish Date (LF)

In critical path method (CPM), the Late Finish Date is the latest time an activity's remaining work can be completed without moving the project completion date, as determined by the schedule network logic and any schedule constraints.

Key Points

  • Calculated during the backward pass of CPM analysis.
  • Driven by network logic, the required project finish date, and any constraints or deadlines.
  • For activities on the critical path, LF equals EF (total float is zero).
  • Total float can be computed as LF - EF (equivalently LS - ES).

Example

A project must complete by day 60. The backward pass shows Activity D has LF = day 40. If Activity D finishes after day 40, the project would slip past day 60, so day 40 is its latest allowable finish without delaying the overall completion.

PMP Example Question

While performing a backward pass, the team wants to find the latest date Activity X can finish without delaying the project finish. Which value are they determining?

  1. Early Finish Date (EF)
  2. Late Start Date (LS)
  3. Late Finish Date (LF)
  4. Free Float

Correct Answer: C — Late Finish Date

Explanation: LF is the latest permissible finish for an activity based on the schedule network, project completion date, and any constraints, identified during the backward pass.

Leadership for Project Managers Course

Lead with clarity, confidence, and real impact. This Leadership for Project Managers course turns day-to-day challenges—unclear priorities, tough stakeholders, and cross-functional friction—into opportunities to guide teams and deliver outcomes that matter.

You’ll learn practical leadership skills tailored to project realities: setting direction without overcontrol, creating alignment across functions, and building commitment even when authority is limited. We go beyond theory with tools you can use immediately—one-sentence visioning, stakeholder influence maps, decision framing, and feedback scripts that actually land.

Expect hands-on frameworks, real-world examples, and guided practice to prepare for tough moments—executive readouts, resistance from stakeholders, and high-stakes negotiations. Downloadable templates and checklists keep everything actionable when the pace gets intense.

Ready to influence without waiting for a bigger title? Join a community of ambitious PMs, sharpen your edge, and deliver with purpose—project after project.



Advance your Lean Six Sigma expertise!

HK School of Management helps you take Lean Six Sigma to the next level—without the overwhelm. Master advanced statistical tools, Excel-based analysis, and real-world improvement techniques to solve complex problems with confidence. For the price of lunch, you get practical templates, guided examples, and hands-on project experience you can use immediately at work. Backed by our 30-day money-back guarantee—zero risk, real impact.

Learn More