Late Finish Date (LF)

In critical path method (CPM), the Late Finish Date is the latest time an activity's remaining work can be completed without moving the project completion date, as determined by the schedule network logic and any schedule constraints.

Key Points

  • Calculated during the backward pass of CPM analysis.
  • Driven by network logic, the required project finish date, and any constraints or deadlines.
  • For activities on the critical path, LF equals EF (total float is zero).
  • Total float can be computed as LF - EF (equivalently LS - ES).

Example

A project must complete by day 60. The backward pass shows Activity D has LF = day 40. If Activity D finishes after day 40, the project would slip past day 60, so day 40 is its latest allowable finish without delaying the overall completion.

PMP Example Question

While performing a backward pass, the team wants to find the latest date Activity X can finish without delaying the project finish. Which value are they determining?

  1. Early Finish Date (EF)
  2. Late Start Date (LS)
  3. Late Finish Date (LF)
  4. Free Float

Correct Answer: C — Late Finish Date

Explanation: LF is the latest permissible finish for an activity based on the schedule network, project completion date, and any constraints, identified during the backward pass.

Project Management Bootcamp

Embark on a transformative journey with our Project Management Bootcamp at HK School of Management. Elevate from beginner to pro using the latest PMBOK and Process Groups Practice Guide. Our unique, engaging approach makes learning interactive and fun, replacing dull slides with dynamic doodles and real-life scenarios.

This hands-on program includes working on two full project plans. The first evolves as you learn, while the second culminates in a comprehensive plan, solidifying your expertise. You'll navigate real-world challenges, backed by quizzes and in-depth analysis, avoiding common pitfalls and setting you on a path to success.

Enhance your learning with downloadable materials and templates, invaluable for your future projects. The course covers essential topics like PMI, PMO, PMBOK, and project management ethics, delving into critical process groups and key areas such as scope, schedule, cost, and stakeholder management.

Learn from seasoned professionals and join a community of enthusiastic lifelong learners. Ready to master project management and lead with confidence? Enroll now and start your transformation!



Advance your Lean Six Sigma expertise!

HK School of Management helps you take Lean Six Sigma to the next level—without the overwhelm. Master advanced statistical tools, Excel-based analysis, and real-world improvement techniques to solve complex problems with confidence. For the price of lunch, you get practical templates, guided examples, and hands-on project experience you can use immediately at work. Backed by our 30-day money-back guarantee—zero risk, real impact.

Learn More