Late Start Date (LS)

In critical path method scheduling, the latest time an activity can begin its remaining work without delaying the project, as dictated by the network logic, the required project finish date, and any schedule constraints.

Key Points

  • Calculated during the backward pass of the critical path method.
  • Driven by successor relationships, the target project completion date, and schedule constraints; tighter limits reduce the LS.
  • Computed as LS = LF - duration, accounting for any leads or lags.
  • On the critical path (zero total float), LS equals ES.

Example

Assume the project must finish by day 60. Activity X has a duration of 6 days, and the backward pass yields a latest finish (LF) of day 40. The late start (LS) is 40 - 6 = day 34. Starting Activity X after day 34 would push its finish beyond day 40 and risk delaying the overall project.

PMP Example Question

An activity has a duration of 4 days and a latest finish (LF) of day 18. What is its late start (LS)?

  1. Day 14
  2. Day 18
  3. Day 22
  4. Cannot be determined without early dates

Correct Answer: A — Late start is day 14

Explanation: LS = LF - duration = 18 - 4 = 14. Early dates are not needed to compute LS from LF and duration.

Advanced Lean Six Sigma — Data-Driven Excellence

Solve complex problems, reduce variation, and improve performance with confidence. This course is designed for professionals who already know the basics and want to apply advanced Lean Six Sigma tools to real business challenges.

This is not abstract statistics or theory-heavy training. You’ll use Excel to perform real analysis, interpret results correctly, and apply tools like DMAIC, SIPOC, MSA, hypothesis testing, and regression without memorizing formulas or relying on expensive software.

You’ll learn how to measure baseline performance, analyze process capability, use control charts to maintain stability, and validate improvements using statistical evidence. Templates, worked examples, and structured walkthroughs help you apply each concept immediately.

Learn through a complete, real-world Lean Six Sigma project and develop the skills to lead data-driven improvements with credibility. If you’re ready to move beyond basics and make decisions backed by data, enroll now and take your Lean Six Sigma expertise to the next level.



Take Control of Project Performance!

HK School of Management helps you go beyond status reports and gut feelings. In this advanced course, you’ll master Earned Value Management (EVM) to objectively measure progress, forecast outcomes, and take corrective action with confidence. Learn how WBS quality drives performance, how control accounts really work, and how to use EAC, TCPI, and variance analysis to make smarter decisions—before projects drift off track. Built around real-world examples and hands-on exercises, this course gives you practical tools you can apply immediately. Backed by our 30-day money-back guarantee—low risk, high impact for serious project professionals.

Learn More