Resource Leveling

A resource balancing approach that modifies the project timeline to align work with resource availability, which can shift activity dates and potentially change the critical path. Related to resource optimization techniques and resource smoothing.

Key Points

  • Used to resolve resource overallocations and conflicts by balancing demand with availability.
  • Adjusts activity start/finish dates based on resource limits; project duration may increase.
  • Can alter the critical path or create new critical paths.
  • Applied after creating a CPM schedule, especially when key resources are limited or constrained.

Example

A software project has only two senior testers, yet several testing tasks are scheduled to run at the same time. The PM levels the testers by delaying some testing activities and resequencing work, which pushes the finish date and changes the critical path but avoids overallocating the testers.

PMP Example Question

To address multiple activities competing for the same limited equipment, the PM delays some tasks and accepts a possible extension of the project duration. What technique is being used?

  1. Resource smoothing
  2. Crashing
  3. Resource leveling
  4. Fast tracking

Correct Answer: C — Resource leveling (balancing work with limited resources)

Explanation: Resource leveling adjusts the schedule to fit resource availability and can extend the timeline or change the critical path, unlike smoothing, which aims to stay within the existing dates.

ICS/OT Incident Response Drills and Exercises

An incident response plan is only a theory until the people who must use it have run it under pressure. This course helps OT engineers, operations leaders, IT responders, and security teams turn a plan on paper into a tested capability.

Define safe states and manual fallback before an incident forces the decision. Build escalation paths, tabletop exercises, and scenarios that expose the gaps a document review cannot find.

Then turn the results into evidence: an after-action report, owned improvements, recovery checks, and a drill cadence that keeps the program alive after the exercise ends.

24 lessons, 2.4 hours. US$47 one-time through HKSM Courses. 30-day money-back guarantee when 50% or less consumed.

Explore the Course


ICS/OT Incident Response Drills and Exercises course preview

Lead with clarity, influence, and outcomes.

HK School of Management offers a practical Leadership for Project Managers course for real projects, tight deadlines, and cross-functional teams. Learn to set direction, align stakeholders, and drive commitment without relying on title. Practical skills, tools, and guidance you can apply right away. Covered by Udemy's 30-day refund policy.

Learn More