Schedule Data

The compiled set of details that define the schedule and support its monitoring, management, and control.

Key Points

  • Includes items such as activity attributes, sequencing details, calendars, resource needs, assumptions, constraints, and milestone lists.
  • Feeds the schedule model and supports baseline creation, change control, and performance tracking.
  • Is maintained and updated as estimates, progress, and risks evolve throughout the project.
  • Enables reporting, forecasting, and what-if analysis for informed decision-making.

Example

On an ERP rollout, the project manager maintains schedule data including task IDs and descriptions, predecessor and successor links, resource calendars, non-working days, milestone dates, and constraints. When a key tester becomes unavailable, the PM updates the schedule data and runs a what-if analysis to re-sequence testing without slipping the go-live date.

PMP Example Question

Which artifact typically contains activity attributes, logical relationships, calendars, assumptions, and constraints used to build and control the project schedule?

  1. Schedule baseline
  2. Schedule data
  3. Project charter
  4. Work performance information

Correct Answer: B — Schedule data

Explanation: Schedule data is the repository of detailed information used to define, manage, and control the schedule. The schedule baseline is the approved plan, the charter authorizes the project, and work performance information summarizes results and variances.

ICS/OT Incident Response Drills and Exercises

An incident response plan is only a theory until the people who must use it have run it under pressure. This course helps OT engineers, operations leaders, IT responders, and security teams turn a plan on paper into a tested capability.

Define safe states and manual fallback before an incident forces the decision. Build escalation paths, tabletop exercises, and scenarios that expose the gaps a document review cannot find.

Then turn the results into evidence: an after-action report, owned improvements, recovery checks, and a drill cadence that keeps the program alive after the exercise ends.

24 lessons, 2.4 hours. US$47 one-time through HKSM Courses. 30-day money-back guarantee when 50% or less consumed.

Explore the Course


ICS/OT Incident Response Drills and Exercises course preview

Launch your career!

HK School of Management provides world-class training in Project Management with AI and Agile Methodologies. Practical skills, tools, and guidance you can apply right away. Covered by Udemy's 30-day refund policy.

Learn More