7.3 Validate Scope

7.3 Validate Scope
Inputs Tools & Techniques Outputs

Replace this with term.

Purpose & When to Use

  • Gain formal sign-off that deliverables meet agreed requirements and acceptance criteria.
  • Reduce rework and disputes by confirming scope completion with the customer or sponsor.
  • Used after internal quality checks confirm correctness of the deliverable.
  • Performed at the end of a phase, iteration, or when a major deliverable is ready.
  • In agile or hybrid work, occurs during reviews or demos where the product owner accepts items.

Mini Flow (How It’s Done)

  • Gather inputs: scope baseline, requirements documentation and traceability matrix, acceptance criteria, and verified deliverables.
  • Plan the review: schedule the session, invite decision-makers, and prepare evidence such as test results and checklists.
  • Run the review or demo: compare the deliverable against acceptance criteria, inspect outputs, and note variances or issues.
  • Decide acceptance: approve, approve with minor conditions, or reject and request corrections.
  • Record outcomes: obtain formal sign-off if accepted, or log defects and raise change requests if not accepted.
  • Update project information: capture acceptance status and issues as work performance information, and record lessons learned.

Quality & Acceptance Checklist

  • Deliverable matches the defined scope and acceptance criteria.
  • All related requirements in the traceability matrix are satisfied.
  • Nonfunctional requirements and constraints are confirmed where applicable.
  • Supporting evidence is available, including test results, measurements, and checklists.
  • User documentation, training materials, and operating procedures are complete.
  • Open defects and risks are documented, owned, and acceptable to the customer.
  • Formal acceptance is captured, including signatures, emails, or tickets.
  • Configuration item identifiers, versions, and baselines are updated after acceptance.
  • Change requests are raised for any new or changed requirements.

Common Mistakes & Exam Traps

  • Confusing internal quality checks with customer acceptance; quality control verifies correctness, while validate scope secures formal sign-off.
  • Assuming a deliverable is accepted because it passed testing; acceptance requires customer or sponsor approval.
  • Skipping the requirements traceability matrix during reviews, which leads to missed criteria.
  • Allowing scope changes in the meeting without a change request and approval through change control.
  • Gold plating or adding extras not requested, which can be rejected and cause delays.
  • Delaying acceptance until project close, increasing risk of late rework.
  • Failing to capture objective evidence of acceptance, such as signed forms or system approvals.
  • Updating baselines after acceptance without formal configuration control.

PMP Example Question

An internal test team confirms a deliverable meets specifications. What should the project manager do next?

  1. Update the scope baseline to reflect the completed work.
  2. Request a customer review to obtain formal acceptance.
  3. Close the project or phase because testing is complete.
  4. Issue a change request to release contingency reserves.

Correct Answer: B — Request a customer review to obtain formal acceptance.

Explanation: After internal verification, the next step is to validate scope with the customer or sponsor and capture formal sign-off. Baseline updates and closure come after acceptance, not before.

Leadership for Project Managers Course

Lead with clarity, confidence, and real impact. This Leadership for Project Managers course turns day-to-day challenges—unclear priorities, tough stakeholders, and cross-functional friction—into opportunities to guide teams and deliver outcomes that matter.

You’ll learn practical leadership skills tailored to project realities: setting direction without overcontrol, creating alignment across functions, and building commitment even when authority is limited. We go beyond theory with tools you can use immediately—one-sentence visioning, stakeholder influence maps, decision framing, and feedback scripts that actually land.

Expect hands-on frameworks, real-world examples, and guided practice to prepare for tough moments—executive readouts, resistance from stakeholders, and high-stakes negotiations. Downloadable templates and checklists keep everything actionable when the pace gets intense.

Ready to influence without waiting for a bigger title? Join a community of ambitious PMs, sharpen your edge, and deliver with purpose—project after project.



Launch your Agile career!

HK School of Management helps you master Agile and Scrum—faster. Learn practical playbooks, AI-powered prompts, and real-world workflows to plan smarter, deliver sooner, and keep stakeholders aligned. For the price of lunch, you’ll get templates, tools, and step-by-step guidance to level up your projects. Backed by our 30-day money-back guarantee—zero risk, clear path to results.

Learn More