7.6 Control Cost

7.6 Control Cost
Inputs Tools & Techniques Outputs

Replace this with term.

Purpose & When to Use

Control Cost keeps project spending on track by comparing actuals to the baseline, forecasting outcomes, and steering corrective actions. Use it throughout the project after the cost baseline is set, with more frequent reviews during high-spend periods or when risks rise.

  • Detect and understand cost variances early.
  • Forecast Estimate at Completion (EAC) and funding needs.
  • Decide and implement corrective or preventive actions.
  • Update the cost baseline only through approved change control.
  • Provide clear, timely cost performance information to stakeholders.

Mini Flow (How It’s Done)

  • Gather Inputs: cost baseline, funding limits, progress data, actual costs, contracts, and prior changes.
  • Measure Progress: confirm earned value using verified work completion, not just time elapsed.
  • Analyze Performance: review cost variance and cost efficiency (e.g., CV, CPI), trends, and reserve usage.
  • Forecast: update EAC and ETC using methods suited to the situation (e.g., CPI-based, bottoms-up for atypical issues).
  • Decide Actions: define corrective or preventive steps, assess impacts, and prepare change requests if baseline or funding must change.
  • Communicate: issue concise cost reports, update stakeholders on variances, forecasts, and approved changes.
  • Implement & Monitor: execute actions, track results, and capture lessons for future cycles.

Quality & Acceptance Checklist

  • Progress measurement method is reliable and agreed (supports earned value where used).
  • Actuals include accrued and committed costs; data sources are reconciled and timely.
  • Variances and trends are calculated correctly and explained with clear drivers.
  • Forecast method matches the situation; assumptions and constraints are documented.
  • To-complete efficiency (e.g., TCPI) is assessed when targeting BAC or a new EAC.
  • Reserves are tracked separately; draws are authorized and logged.
  • Funding limits and cash flow are respected; no unapproved overruns exist.
  • Contract charges align to delivered work; change orders and claims are reflected.
  • Baseline updates occur only after formal approval and are version-controlled.
  • Stakeholder reports are timely, clear, and actionable.

Common Mistakes & Exam Traps

  • Confusing total budget with the cost baseline; remember management reserve is outside the baseline.
  • Using time elapsed as a proxy for progress, causing incorrect earned value and misleading variances.
  • Thinking a negative cost variance is good; negative CV indicates overrun.
  • Re-baselining to hide variances instead of analyzing root causes and taking action.
  • Ignoring committed costs and accruals, which leads to late surprises.
  • Picking the wrong EAC method; use CPI-based for persistent performance, bottoms-up for one-off issues, or combine schedule impact if it drives cost.
  • Skipping change control when the baseline will be breached; raise a change request when overrun is unavoidable.
  • Not updating risks and reserves after cost variances or forecast changes.
  • Failing to coordinate with procurement on contract changes that affect cost.

PMP Example Question

Your project’s CPI is 0.85 and trends show the overrun will continue. The sponsor asks you to stay within the current budget. What should you do next?

  1. Immediately update the cost baseline to a higher amount.
  2. Submit a change request for more funds without further analysis.
  3. Analyze cost drivers and propose corrective actions to improve performance before requesting changes.
  4. Ignore CPI because schedule is on track.

Correct Answer: C — Analyze cost drivers and propose corrective actions to improve performance before requesting changes.

Explanation: First, investigate variances and try corrective actions. If an overrun remains unavoidable, then follow change control to adjust funding or scope.

Project Management Bootcamp

Embark on a transformative journey with our Project Management Bootcamp at HK School of Management. Elevate from beginner to pro using the latest PMBOK and Process Groups Practice Guide. Our unique, engaging approach makes learning interactive and fun, replacing dull slides with dynamic doodles and real-life scenarios.

This hands-on program includes working on two full project plans. The first evolves as you learn, while the second culminates in a comprehensive plan, solidifying your expertise. You'll navigate real-world challenges, backed by quizzes and in-depth analysis, avoiding common pitfalls and setting you on a path to success.

Enhance your learning with downloadable materials and templates, invaluable for your future projects. The course covers essential topics like PMI, PMO, PMBOK, and project management ethics, delving into critical process groups and key areas such as scope, schedule, cost, and stakeholder management.

Learn from seasoned professionals and join a community of enthusiastic lifelong learners. Ready to master project management and lead with confidence? Enroll now and start your transformation!



Launch your career!

HK School of Management provides world-class training in Project Management, Lean Six Sigma, and Agile Methodologies. Just for the price of a lunch you can transform your career, and reach new heights. With 30 days money-back guarantee, there is no risk.

Learn More