Large Scale Scrum (LESS)

A product development framework that expands Scrum to many teams by offering scaling guidance while keeping Scrum's original goals and principles intact.

Key Points

  • Scales Scrum for multiple teams working on a single product.
  • Relies on one Product Backlog and one Product Owner for the whole product.
  • Adds minimal extra roles and artifacts to preserve core Scrum.
  • Promotes shared Definition of Done and frequent cross-team integration each Sprint.

Example

A company has six teams building a unified analytics platform. Using Large Scale Scrum (LESS), they maintain one Product Backlog prioritized by a single Product Owner. Teams hold a joint Sprint Planning, develop in parallel, integrate continuously, and present one increment at a combined Sprint Review.

PMP Example Question

Which approach extends Scrum for many teams with lightweight scaling guidance while preserving Scrum's original intent?

  1. Scaled Agile Framework (SAFe)
  2. Scrum of Scrums meeting technique
  3. Large Scale Scrum (LESS)
  4. PRINCE2

Correct Answer: C — Large Scale Scrum (LESS)

Explanation: LESS explicitly scales Scrum with guidance that keeps the framework lean and aligned with Scrum's purposes; SAFe adds additional layers, Scrum of Scrums is a coordination practice, and PRINCE2 is not Scrum-based.

Project Management with AI: From Initiation to Closing

Build a practical project management process from initiation to closing with our Project Management: From Initiation to Closing with AI course. Learn how to move from informal project coordination to a structured, repeatable approach using PMBOK-aligned workflows, real examples, and professional templates.

This hands-on course follows a complete project lifecycle. You will learn how to write a project charter, define scope, build a work breakdown structure, develop a schedule, estimate costs, manage risks, engage stakeholders, execute the work, monitor performance, and close the project properly.

You will also learn how to use AI tools to accelerate project management work. The course includes reusable prompts, downloadable templates, assignments, and worked examples that show how project documents connect from one stage to the next.

The course is designed for professionals, team leads, coordinators, analysts, and new project managers who need practical skills they can apply at work. Enroll now and build the confidence to manage projects with structure, clarity, and control.

Explore the Course


Build complete project plans in minutes with AI

Learn how to use AI to create charters, WBSs, schedules, risk registers, and executive reports while staying in control. This course gives you prompt templates and practical workflows based on real project work. Practical skills, tools, and guidance you can apply right away. Covered by Udemy's 30-day refund policy.

Learn More