7.11 Control Procurements
Replace this with term.
Purpose & When to Use
- Ensure contracted work meets scope, quality, schedule, and cost expectations.
- Validate deliverables, approve or reject work, and authorize payments tied to contract terms.
- Manage change requests, claims, and disputes using the agreed procedures.
- Track seller performance with objective data and take corrective or preventive action.
- Apply from contract award through final acceptance and contract closure for any external procurement.
Mini Flow (How It’s Done)
- Start with the contract, procurement management plan, requirements, and acceptance criteria.
- Collect performance data from the seller (status reports, milestones, quality results, KPIs, forecasts).
- Inspect and test deliverables; conduct audits or site visits when needed.
- Record acceptance or rejection against criteria; issue nonconformance reports and request corrections as required.
- Process changes through the formal change control process; document approved contract modifications.
- Hold regular performance reviews; manage communications and relationships with the seller and stakeholders.
- Identify, log, and resolve issues and claims; negotiate per the contract and escalate disputes as defined.
- Match invoices to accepted work and milestones; authorize payments per terms and retainage rules.
- Update risks, assumptions, and lessons learned; maintain complete procurement records.
- Prepare for closure: verify final acceptance, confirm deliverables and warranties, release resources, and close the contract.
Quality & Acceptance Checklist
- Acceptance criteria and scope statements are clearly traceable to each deliverable.
- Objective evidence of quality is available (tests, inspections, certificates) and reviewed.
- All nonconformities are resolved or formally waived by authorized roles.
- Performance metrics meet thresholds (schedule, cost, service levels).
- Configuration and version control are applied; only approved baselines are used.
- All change orders are formally approved and reflected in updated contract documents.
- Deliverables are complete, with required documentation, licenses, and warranties.
- Regulatory, safety, security, and data requirements are met and documented.
- Invoice amounts match accepted work, milestones, and contract rates; taxes and retention are correct.
- Approvals and sign-offs are obtained from the authorized buyer representatives.
Common Mistakes & Exam Traps
- Paying invoices before formal acceptance or without matching to contract milestones.
- Agreeing to scope or schedule changes informally with the seller instead of using change control.
- Confusing product quality checks with contract compliance; both are required.
- Ignoring the contract’s remedies, penalties, or incentives when performance slips.
- Letting undocumented “directional” emails alter the scope or terms.
- Failing to document issues, claims, and resolutions in the procurement records.
- Assuming fixed-price means no monitoring; the buyer still verifies deliverables and compliance.
- Applying the wrong payment logic for contract type (e.g., paying T&M hours without validation).
- Escalating disputes outside the process defined in the contract (e.g., skipping negotiation or mediation steps).
- Closing the project but forgetting to close the contract or release guarantees and retainage.
PMP Example Question
A seller submits an invoice after delivering a milestone. Testing found minor defects, and the contract requires written acceptance for each milestone. What should the project manager do next?
- Approve the invoice to maintain a good relationship with the seller.
- Raise a change request to relax the acceptance criteria for this milestone.
- Reject the deliverable and request correction according to the contract.
- Approve the invoice but hold payment until defects are fixed.
Correct Answer: C — Reject the deliverable and request correction according to the contract.
Explanation: Acceptance must follow the contract and criteria; with defects present and no written acceptance, the PM should withhold approval and request fixes before payment.
HKSM