7.4 Control Scope

7.4 Control Scope
Inputs Tools & Techniques Outputs

Replace this with term.

Purpose & When to Use

Control Scope keeps the project focused on the agreed deliverables. It verifies what is completed against the scope baseline and manages any requested changes through a formal process. Use it throughout the project once the scope baseline is set, and apply it regularly in both predictive and adaptive life cycles.

Mini Flow (How It’s Done)

  • Review the scope baseline: scope statement, WBS, and WBS dictionary.
  • Collect actuals: completed work, deliverable status, and requirement fulfillment from the requirements traceability matrix.
  • Compare actuals to the baseline and analyze variances and trends.
  • Identify unapproved additions (scope creep) and stop them from proceeding.
  • Evaluate needed changes; submit formal change requests with impact analysis on schedule, cost, quality, risks, and benefits.
  • Process changes through integrated change control; implement only approved changes.
  • Update the scope baseline, WBS, RTM, and related plans and documents after approval.
  • Communicate status, variances, and decisions to stakeholders; adjust backlog or release plan in adaptive approaches.

Quality & Acceptance Checklist

  • Scope baseline is current, version-controlled, and accessible.
  • Each deliverable has clear, measurable acceptance criteria.
  • All scope changes are submitted, reviewed, and approved or rejected formally.
  • Requirements traceability matrix shows status, tests, and acceptance for each requirement.
  • Approved changes are reflected in the WBS, schedule, budget, and risks.
  • Variance analysis (e.g., scope performance, trend) is documented with actions.
  • Instances of gold plating or scope creep are recorded and corrected.
  • Stakeholder communications and acceptance records are complete and archived.

Common Mistakes & Exam Traps

  • Confusing Control Scope (monitor and manage changes) with Validate Scope (formal acceptance of completed deliverables).
  • Allowing team or stakeholders to add features without approval (gold plating or scope creep).
  • Updating schedule or cost without updating the scope baseline and WBS after a change is approved.
  • Skipping impact analysis before submitting or deciding on a change request.
  • Not using the requirements traceability matrix to verify each requirement’s status and tests.
  • Treating defect repair as a scope change without checking if it restores the baseline deliverable.
  • Assuming internal completion equals acceptance; acceptance must match stated criteria.

PMP Example Question

A stakeholder asks the team to add a minor feature. The team has started work on it to save time. What should the project manager do next?

  1. Allow the team to finish since the change is small and will delight the customer.
  2. Submit a formal change request and assess impacts before any additional work continues.
  3. Update the WBS and schedule to include the extra work and inform stakeholders.
  4. Reject the change immediately and forbid any future change requests.

Correct Answer: B — Submit a formal change request and assess impacts before any additional work continues.

Explanation: Only approved changes should be implemented. Control Scope prevents scope creep and ensures changes go through formal change control with impact analysis.

Project Management Bootcamp

Embark on a transformative journey with our Project Management Bootcamp at HK School of Management. Elevate from beginner to pro using the latest PMBOK and Process Groups Practice Guide. Our unique, engaging approach makes learning interactive and fun, replacing dull slides with dynamic doodles and real-life scenarios.

This hands-on program includes working on two full project plans. The first evolves as you learn, while the second culminates in a comprehensive plan, solidifying your expertise. You'll navigate real-world challenges, backed by quizzes and in-depth analysis, avoiding common pitfalls and setting you on a path to success.

Enhance your learning with downloadable materials and templates, invaluable for your future projects. The course covers essential topics like PMI, PMO, PMBOK, and project management ethics, delving into critical process groups and key areas such as scope, schedule, cost, and stakeholder management.

Learn from seasoned professionals and join a community of enthusiastic lifelong learners. Ready to master project management and lead with confidence? Enroll now and start your transformation!



Lead with clarity, influence, and outcomes.

HK School of Management brings you a practical, no-fluff Leadership for Project Managers course—built for real projects, tight deadlines, and cross-functional teams. Learn to set direction, align stakeholders, and drive commitment without relying on title. For the price of a lunch, get proven playbooks, and downloadable templates. Backed by a 30-day money-back guarantee—zero risk, high impact.

Learn More