Earned Schedule (ES)

A time-based extension of Earned Value Management that assesses schedule performance in units of time rather than cost.

Key Points

  • ES translates the earned value (EV) into the point in time on the planned value curve where that EV would have been planned.
  • Core indicators: SV(t) = ES - AT (schedule variance in time) and SPI(t) = ES / AT (schedule performance index in time), where AT is the actual time elapsed to the status date.
  • Unlike traditional SPI and SV, ES-based metrics continue to show meaningful schedule performance near project completion.
  • Helps forecast finish dates, assess schedule buffers, and integrate time-focused insights with standard EVM cost metrics.

Example

A project is at week 20 (AT = 20). The earned value achieved to date equals the planned value that was scheduled for week 18. Therefore, ES = 18 weeks. SV(t) = 18 - 20 = -2 weeks (behind schedule), and SPI(t) = 18 / 20 = 0.90.

PMP Example Question

At the status date, AT = 24 weeks and ES = 21 weeks. What is the best interpretation of these results?

  1. The project is 3 weeks under budget.
  2. The project is 3 weeks ahead of schedule.
  3. The project is 3 weeks behind schedule based on time-focused EVM.
  4. The project is performing as planned because SPI is 1.0.

Correct Answer: C — Earned Schedule indicates the work accomplished corresponds to week 21 while 24 weeks have elapsed.

Explanation: SV(t) = ES - AT = 21 - 24 = -3 weeks, showing the project is 3 weeks behind schedule using the Earned Schedule method.

ICS/OT Cybersecurity Fundamentals — Security Built for Industrial Systems

Industrial control systems cannot be secured like ordinary IT. A forced reboot, aggressive scan, or incompatible patch can interrupt production and create real safety consequences. Effective OT security begins with understanding the systems, constraints, and risks unique to industrial environments.

This course gives IT professionals, engineers, operators, and security practitioners a practical foundation in ICS threats, zone and conduit design, risk assessment, passive asset visibility, and vendor evaluation. You will learn how IEC 62443, NIST CSF, and MITRE ATT&CK for ICS apply where availability and safety come first.

Eight reconstructed incidents—including Stuxnet, Triton, Ukraine 2015, Colonial Pipeline, and PIPEDREAM—show how attackers move through OT environments, what they target, and which defenses could have changed the outcome.

Watch the course preview, then build the vocabulary, frameworks, and judgment needed to take credible first steps in ICS/OT cybersecurity.

Explore the Course


ICS/OT Cybersecurity Fundamentals course preview

Build the Sprint Reporting System, Not Another Prompt

AI Systems with Claude is our own course for Scrum Masters and Agile Project Managers, taught against one running project across eight teaching sections. You build five working systems and keep them: the sprint report machine, the retro intelligence system, the stakeholder comms engine, the backlog health monitor, and the risk and dependency tracker. Direct from HK School of Management, not on Udemy.

See What Is Included