Float

The amount of schedule flexibility for an activity or path, expressed as how long it can be delayed without creating a defined impact. In practice, this flexibility is measured as total float when the impact is the project finish date, or as free float when the impact is the start of the immediate successor.

Key Points

  • Also called slack. See total float and free float.
  • Calculated via critical path method by comparing early and late dates from forward and backward passes.
  • Activities on the critical path typically have zero total float; negative float indicates a schedule that violates an imposed date.
  • Float is consumable and can be reduced by changes, risk responses, or resource leveling, so it should be monitored and managed.

Example

In a sequence A -> B -> C, B is planned to finish on day 6 and C is scheduled to start on day 9. B can slip to finish as late as day 9 without delaying C, so B has 3 days of free float. If the project finish depends on C, B also has 3 days of total float.

PMP Example Question

Which statement best describes float in a project schedule?

  1. The budget reserve available to absorb cost overruns.
  2. The time an activity can slip before affecting a defined schedule date, such as the project finish or a successor's start.
  3. The difference between optimistic and pessimistic duration estimates.
  4. Idle time caused by resource underutilization.

Correct Answer: B — time an activity can slip before affecting a specified schedule date

Explanation: Float represents schedule flexibility; common forms are total float (relative to project finish) and free float (relative to the successor's start).

Project Management with AI: From Initiation to Closing

Build a practical project management process from initiation to closing with our Project Management: From Initiation to Closing with AI course. Learn how to move from informal project coordination to a structured, repeatable approach using PMBOK-aligned workflows, real examples, and professional templates.

This hands-on course follows a complete project lifecycle. You will learn how to write a project charter, define scope, build a work breakdown structure, develop a schedule, estimate costs, manage risks, engage stakeholders, execute the work, monitor performance, and close the project properly.

You will also learn how to use AI tools to accelerate project management work. The course includes reusable prompts, downloadable templates, assignments, and worked examples that show how project documents connect from one stage to the next.

The course is designed for professionals, team leads, coordinators, analysts, and new project managers who need practical skills they can apply at work. Enroll now and build the confidence to manage projects with structure, clarity, and control.

Explore the Course


Take Control of Project Performance!

HK School of Management helps you go beyond status reports and gut feelings. In this advanced course, you’ll master Earned Value Management (EVM) to objectively measure progress, forecast outcomes, and take corrective action with confidence. Learn how WBS quality drives performance, how control accounts really work, and how to use EAC, TCPI, and variance analysis to make smarter decisions—before projects drift off track. Built around real-world examples and hands-on exercises, this course gives you practical tools you can apply immediately. Backed by our 30-day money-back guarantee—low risk, high impact for serious project professionals.

Learn More