Monitor and Control Project Work

An ongoing activity that measures, analyzes, and communicates overall project performance to ensure outcomes align with the objectives set in the project management plan.

Key Points

  • Continuously compares actual results with the plan to detect variances in scope, schedule, cost, and quality.
  • Converts work performance data into information and reports for decision-making and stakeholder communication.
  • Identifies issues and recommends corrective or preventive actions, often resulting in change requests.
  • Updates forecasts and project documents and provides inputs to integrated change control when changes are needed.

Example

The project manager reviews earned value metrics and status reports, finds the schedule is slipping, forecasts a later finish date, prepares a performance report for stakeholders, and submits a change request to add resources to recover the schedule.

PMP Example Question

Which process analyzes performance data, prepares work performance reports, and recommends actions to keep the project aligned with the plan?

  1. Direct and Manage Project Work
  2. Monitor and Control Project Work
  3. Perform Integrated Change Control
  4. Control Quality

Correct Answer: B — Monitor and Control Project Work

Explanation: This process tracks and analyzes overall performance, produces reports, and suggests corrective or preventive actions. Direct and Manage executes the work, Integrated Change Control approves changes, and Control Quality inspects deliverables.

Advanced Project Management — Measuring Project Performance

Move beyond guesswork and status reporting. This course helps you measure real progress, spot problems early, and make confident decisions using proven project performance techniques. If you manage complex projects and want clearer visibility and control, this course is built for you.

This is not abstract theory. You’ll work step by step through Earned Value Management (EVM), learning how cost, schedule, and scope come together to show true performance. You’ll build a solid foundation in EVM concepts, understand why formulas work, and learn how performance data actually supports leadership decisions.

You’ll master Work Breakdown Structures (WBS), control accounts, and budget baselines, then apply core EVM metrics like EAC, TCPI, and variance analysis. Through a detailed real-world example, you’ll forecast outcomes, analyze trends, and understand contingencies and management reserves with confidence.

Learn how experienced project managers monitor performance, communicate results clearly, and take corrective action before projects slip. With practical exercises and hands-on analysis, you’ll be ready to apply EVM immediately. Enroll now and start managing performance with clarity and control.

Explore the Course


Launch your career!

HK School of Management offers training in project management, job-search strategies, and career growth. Practical skills, tools, and guidance you can apply right away. Covered by Udemy's 30-day refund policy.

Learn More