Introduction

Here is something most people learn the hard way: most of the work on an OT incident response plan is not the writing. It happens before the first chapter and after the last one. A senior sponsor, the right team, the interviews across every shift, the approval and the upkeep decide whether anyone ever uses the plan. The writing sits in the middle.

You are probably reading this because someone handed you the job. Maybe your site has an IT incident response plan that says nothing about the plant. Maybe there is an old OT plan on a shelf that nobody on shift has read. Either way, the usual first move is to download a template, fill in the blanks and get it signed. Then an alarm comes in at night, and the operator on shift has never seen the plan. Templates are easy to find. The method behind a plan that works is not: who sponsors it and who writes it, what it says about safe states and shutdown authority, and how it stays current as the plant changes.

Three Answers Your Plan Will Give

By the end of this book, your plan will answer three questions most plans dodge. Who decides? What do the people on shift do in the first hour? And when is the plant safe to restart? You build the plan one chapter at a time, in an order that follows how those decisions depend on each other, and every chapter of this book fills one chapter of a real plan template. Each one shows the worksheets filled in for Cedar Ridge, an illustrative water treatment plant, so you can see what a finished answer looks like before you write your own. The Cedar Ridge numbers are illustrative: borrow the structure, not the figures.

StageBook chaptersWhat the plan gains
1. Set up the plan project1 Before You Write; 2 Gather the InputsAuthority, a charter and a named sponsor; the planning team; the rules and contracts the plan must meet; interviews across every shift; critical functions, scenarios and safe states.
2. Decide what counts and who decides3 Definitions and Classification; 4 Organization and CommandThe line between an event and an incident; who declares; severity in the plant's own risk language; activation levels; every role mapped to a real job, with alternates; who may isolate, shut down or call the police.
3. Write the response and recovery5 Response Procedures; 6 Recovery and Return to Service; 7 Playbooks and the Readiness LibrarySteps a stressed reader can follow; the first-hour procedure; legal clauses; one notification matrix for the US, the EU, Canada and Australia; recovery objectives and restart criteria; playbooks and a console card.
4. Approve it and keep it current8 Make It RealTwo review rounds and four signatures; a compliance annex for auditors; review dates, change triggers and controlled copies; every audience briefed on its part.
5. Prove it on a new site9 Kestrel PrairieA complete plan for a fictional electric cooperative, scored against a model plan the way an approver would.

Three real incidents run through the book, each testing the worksheets in the chapter where it appears. Jaguar Land Rover in 2025 shows how one incident can stop a whole supply chain. The 2022 attack on Kojima Industries, a Toyota supplier, shows how someone else's incident can trigger your plan. And Clorox in 2023 shows why an outsourced helpdesk belongs in your response.

How to Use This Book

The plan template at the center of this book has eight chapters, a regulatory compliance annex and five appendices. Appendix A lists the templates and worksheets, with a link to download them as printable PDFs and editable Word and Excel files, together with the filled Cedar Ridge examples. Keep your copy of the template open and fill in each chapter while the topic is fresh, because later chapters reuse the reference numbers and decisions from earlier ones. Appendix B lists the free public guides and templates the chapters mention.

Every chapter ends with a table of the standards, laws and guidance it relies on: who each one applies to, what it asks of that part of the plan, and its status when this book was checked in October 2026. Rules change, so check the current version of any regulation before your plan relies on it. Nothing in this book is legal advice. If you already know a topic, skim the chapter, but still fill in the worksheet; the worksheets are what turn reading into a plan.

The book stops where testing begins. It hands your plan to testing in Chapter 8 and says what must be tested and by when, but how to design and run exercises is a separate discipline. Everything before that point is here.

What's Next

Chapter 1 starts where most plans go wrong: before anyone writes a word. It sets up the plan as a project, with a policy, a charter, a sponsor and a team, and lists the rules your plan must satisfy.

AI Systems with Claude, for Scrum Masters and Project Managers

Most AI pilots in project management do not fail on the model. They fail because somebody pointed the thing at a decision instead of at a task. This course is built around that distinction, and around the work that follows once you get it right.

Eight teaching sections, taught against one running project from the first lecture to the last. You watch a system get built, then you build the same one against your own sprint. Nothing here is a demo that works only on the example.

You finish with five working systems and you keep them. The sprint report machine turns your board export and standup notes into the report you currently write by hand. The retro intelligence system tells you what the team keeps saying, not just what it said this time. The stakeholder comms engine drafts the update in the register the audience expects. The backlog health monitor flags the quiet decay nobody has time to check for. The risk and dependency tracker follows the chains that actually bite.

Seventy-six working files ship with it, across four sections, so every system is built against real sprint data rather than material invented for a slide. Four sprints of retrospectives, board exports, standup notes, backlog and risk data.

Explore the Course


Build the Sprint Reporting System, Not Another Prompt

AI Systems with Claude is our own course for Scrum Masters and Agile Project Managers, taught against one running project across eight teaching sections. You build five working systems and keep them: the sprint report machine, the retro intelligence system, the stakeholder comms engine, the backlog health monitor, and the risk and dependency tracker. Direct from HK School of Management and Technology, not on Udemy.

See What Is Included