Lead

A time offset that allows a successor activity to begin (or finish) earlier than its predecessor would normally permit; it is the amount of time the successor is pulled forward relative to the predecessor.

Key Points

  • Often implemented as a negative lag in scheduling tools (e.g., FS - 2d), creating overlap between activities.
  • Can shorten the overall schedule by enabling parallel work, but may raise risk or rework if used excessively.
  • Should be logically justified and documented; do not use leads to mask schedule problems.
  • Applies to any dependency type (FS, SS, FF, SF), with FS plus lead being the most common case.

Example

Development and System Testing have a finish-to-start relationship. By applying a 2-day lead, Testing begins 2 days before Development is fully complete, allowing overlap and earlier feedback.

PMP Example Question

Activity B has a finish-to-start dependency on Activity A with a lead of 3 days. What does this indicate?

  1. B must start 3 days after A finishes.
  2. B can start 3 days before A finishes.
  3. B must finish 3 days before A starts.
  4. A can start 3 days earlier than planned.

Correct Answer: B — The successor starts 3 days earlier than the predecessor finishes.

Explanation: A lead advances the successor relative to the predecessor. With FS and a 3-day lead, B begins 3 days before A's finish.

Leadership for Project Managers Course

Lead with clarity, confidence, and real impact. This Leadership for Project Managers course turns day-to-day challenges—unclear priorities, tough stakeholders, and cross-functional friction—into opportunities to guide teams and deliver outcomes that matter.

You’ll learn practical leadership skills tailored to project realities: setting direction without overcontrol, creating alignment across functions, and building commitment even when authority is limited. We go beyond theory with tools you can use immediately—one-sentence visioning, stakeholder influence maps, decision framing, and feedback scripts that actually land.

Expect hands-on frameworks, real-world examples, and guided practice to prepare for tough moments—executive readouts, resistance from stakeholders, and high-stakes negotiations. Downloadable templates and checklists keep everything actionable when the pace gets intense.

Ready to influence without waiting for a bigger title? Join a community of ambitious PMs, sharpen your edge, and deliver with purpose—project after project.



Take Control of Project Performance!

HK School of Management helps you go beyond status reports and gut feelings. In this advanced course, you’ll master Earned Value Management (EVM) to objectively measure progress, forecast outcomes, and take corrective action with confidence. Learn how WBS quality drives performance, how control accounts really work, and how to use EAC, TCPI, and variance analysis to make smarter decisions—before projects drift off track. Built around real-world examples and hands-on exercises, this course gives you practical tools you can apply immediately. Backed by our 30-day money-back guarantee—low risk, high impact for serious project professionals.

Learn More